Client / Site: NKT Cables – HVDC Cable Route, East Coast Landfall, UK
NKT needed specialist diving support for a critical phase of their HVDC (High Voltage Direct Current) export cable project. The operation involved HDD diving support for a Horizontal Directional Drilling landfall connection, where underground drilling creates a pathway from land to sea for major cable installations.
This HDD diving support operation presented multiple technical challenges:
The client required seamless HDD diving support with absolute precision, as the offshore lay vessel commitments meant there was no room for error or delays.
Dagger Diving Services deployed a specialist HDD diving support team with advanced surface-supplied diving systems and precise tidal planning capabilities.
Pre-Operation Preparation Our HDD diving support specialists conducted comprehensive subsea verification of the HDD exit trench using tactile and acoustic methods. Working in challenging visibility conditions, divers systematically removed silt, gravel, and clay plugs using suction and water-dredging techniques to ensure a clear drill path.
Precision Positioning Systems Pull-head alignment was achieved using tensioned rigging and subsea positioning markers, installed by our dive team in advance. This preparation ensured highly-accurate positioning for the critical cable pull-in phase.
Advanced Diving Operations
Critical Pull-In Phase
During the actual cable pull-in, our HDD diving support team engaged and secured the pull-head for cable transition through the HDD duct, standing by throughout the full tension pull-in process with continuous topside communication.
Quality Assurance
Post-installation, divers conducted comprehensive as-built checks, documenting depth of burial, duct integrity, and slack management at the trench interface to ensure long-term cable protection.
Flawless Execution – First-Time Success
Our HDD diving support operation delivered exactly what NKT needed: precision execution with zero delays and perfect technical results.
Operational Excellence:
Technical Achievement:
Documentation & Compliance:
Project Impact: NKT remained on schedule with their wider export cable programme, enabling the renewable energy project to proceed without costly delays.
Safety & Standards: All operations were executed under IMCA D014/D018 and ISO 9001, 45001, 14001 standards, with full environmental protection, subsea quality assurance, and trench interface validation. Coordination with marine assets met all navigational and project safety protocols.
Planning a cable installation project requiring diving support? Dagger Diving Services specializes in precision subsea operations for HDD landfall connections. Contact us today to discuss your HDD diving support requirements.
More about our sub-sea cable laying services